EFH Co. sold the land, provided development assistance and performed design/build construction services to Quality Ingredients as they built their new office, dry powder manufacturing and warehouse facility in Burnsville.

The considerable elevation change on the site from east to west was leveraged to design office space with a full view of the production facility. The building was constructed using Wells Concrete Precast panels including roof, walls and structural beams and columns. The structural capability of the panels permitted the west elevation to be buried with approximately 14 feet of grade against the exterior wall. Total construction time for the project was 6 months.

Building Type: 
Industrial / Manufacturing / Office
Location: 
Burnsville, MN
Square Feet: 
40,000